How Long Does It Take to Build a Pool in North Texas?


I get asked this question at almost every first consultation. And I understand why. You have a vision for your backyard, you want to know when you can start living in it, and you want a straight answer.
Here is the honest one: the timeline depends on decisions made before a single shovel hits the ground. I have built enough custom pools across North Texas to know that the projects that go smoothly are the ones where we took the time upfront to get everything right. The ones that drag on are almost always the ones where someone rushed the early stages.
Let me walk you through every phase of a custom pool build so you know exactly what to expect and when.
Phase 1: Design Consultation and Planning
Typical timeline: 4 to 8 weeks
This is where I spend the most time, and it is time well spent.
I work directly with every client through the design process. Before anything is drawn, I need to understand how you use your backyard, who is using it, how you entertain, and what the property can actually support. I produce 3D renderings so you can see the design before we commit to building it. Materials, finishes, water features, fire elements, outdoor kitchens, and any other integrations are all locked in during this phase.
Changes during design are easy. Changes during construction are expensive and time-consuming. The time we spend here protects your investment and your timeline.
Once the design is approved, we move into permitting.
Phase 2: Permitting
Typical timeline: 2 to 6 weeks
This is the phase most homeowners do not think about until it is in front of them.
I manage the permitting process for every project. You will not be navigating city offices or chasing paperwork on your own. But I want you to understand that permitting timelines are controlled by your city or county, not by me. In Ellis County communities like Midlothian and Waxahachie, we typically see residential pool permits come back in two to four weeks. In some DFW municipalities, it can take longer.
Construction cannot start until those permits are issued. That is not something I can work around, and any builder who tells you otherwise is not someone you should trust on your property.
Phase 3: Excavation
Typical timeline: 1 to 3 days
Once permits are in hand, we move fast (depending on weather).
The footprint, depth, and shape of your pool are already precisely laid out from the design phase, so excavation goes quickly. Most residential pools I build in North Texas are excavated in one to three days.
I want to mention soil here because it matters in this region. Black gumbo clay is common throughout Ellis County and much of the DFW area. It behaves differently than sandy soil and requires experience to work with properly. I factor local soil conditions into both the schedule and the structural engineering of every project I take on. There are no surprises mid-build when you account for it at the start.
Phase 4: Shell Construction, Steel, Plumbing, and Gunite
Typical timeline: 2 to 4 weeks
This is where your pool takes structural shape.
The rebar steel framework is installed and inspected. Plumbing and electrical conduit are roughed in. Then we spray the shell with gunite, which is the concrete material that forms the walls and floor of your pool. It is the structural foundation of everything that follows.
After the shell is placed, it has to cure for a minimum of 28 days. This is a structural requirement, not a preference. I have seen what happens when builders cut that time short. Cracked shells. Compromised integrity. Problems that show up years later and cost far more to fix than the time that was saved. I do not cut cure time, and I would encourage you to ask any builder you speak with whether they do.
Phase 5: Decking, Coping, and Tile
Typical timeline: 2 to 3 weeks
This is where the environment around the water starts to come together.
Coping goes in along the pool edge. Tile work is completed. Decking, whether that is travertine, cool deck, pavers, or another material we selected together during design, is installed with precision. If your project includes water features, fire features, an outdoor kitchen, or a covered structure, those elements are being built out concurrently during this phase.
Every finish you see in the final product was a decision we made together. Nothing is an afterthought.
Phase 6: Equipment, Plaster, and Water
Typical timeline: 1 to 2 weeks
We are close now. This is the final phase.
The equipment, pump, filter, heater, automation system, and any water feature components, gets installed and commissioned. Then the interior plaster finish is applied. Plaster goes in fast, typically in a single day, but what happens next is what I have been working toward since the first time we sat down together.
Water fills the pool. Chemistry gets balanced. Your backyard becomes what you imagined.
So What Is the Total Timeline?
From first consultation to your first swim, here is what to realistically plan for:
• Simple to moderately complex pool: 4 to 5 months
• Complex design with outdoor kitchen, fire features, or full backyard integration: 5 to 7 months
• Projects requiring additional engineering for soil, grade, or site access: add 2 to 4 weeks
North Texas summers are hot and construction moves quickly in the heat. Winter months can occasionally introduce short delays when freezing temperatures affect concrete work. I plan around that wherever I can.
When Should You Start the Conversation?
I work with a limited number of projects at one time. That is a deliberate choice. Every client I take on deserves my full attention, and I am not willing to compromise that by overextending. What that means for you is that the DFW luxury pool market books out, and starting early is not just about your timeline, it’s about working together with availability, seasons, and more.
I would rather have that conversation with you now so we can build something extraordinary together on a schedule that works.
Call me at 817-225-1071 or visit backyardsbytaborsky.com to schedule your consultation.
Why Work With Me
I have been designing and building custom luxury pools across North Texas for years. I have earned four National Awards and two Regional Awards for my work. More importantly, I have built relationships with clients who trust me to treat their home like it is my own.
I am not running a production operation. Every project I take on is a personal commission. You will work directly with me from the first conversation to the final walkthrough.
If you are considering a custom pool in Midlothian, Waxahachie, Mansfield, or anywhere near Ellis County, I would love to talk about what we can build together.
The best time to start is always sooner than you think.